|
|
|||
|
Tel/Fax 01923 682300 |
|||
|
|
Bookmark this site. | ||
|
|
The photographs above show the various stages of construction of the load cell. The left photo shows the preparation of the pile for the load cell. The middle photo shows the completed load cell fitted with its 3 mm soft membrane and reinforcing bars with pressure pads to link with the raft. The right photo shows the first layers of the raft reinforcement installed around the cell.
The above plot shows the load carried by the pile. The reduction in load in 1981 was due to the foundation contractor removing his plant from the site. The rapid increase in load was due to the main building works, followed by the less steep fitting out stage. Since January 87 there has been a slow reduction in load, thought to be due to a rise in the water level in the area. The general fall in load was also recorded by 4 raft pressure cells. The load cell and the raft pressure cells only monitor effective pressure, i.e. water pressure can pass either side of the soft membrane. |
|||||