Construction Monitoring Control Systems Ltd

Tel/Fax  01923 682300

 
 
  Bookmark this site.
 


  1. Index
  2. CMCS at BRE
  3. Development of AMS
  4. Non-destructive testing of Marine Jetties
  5. Fixed sensor monitoring of Diaphragm walls
  6. Monitoring Buildings during Redevelopment
  7. Tunnel Monitoring
  8. Embankment Systems
  9. Loggers
  10. Tunnel Distortion Monitoring
  11. In-place tilt monitoring system
  12. Tunnels Interaction System
  13. Re-Development of Small Properties
  14. Viaducts
  15. DLR at Mansion House
  16. Tunnel Monitoring System (Discrete beams)
  17. CTRL 240
  18. Dams
  19. Electro-levels
  20. Movement indicators
  21. Results of Charing Cross Load Cells
  22. Non-destructive testing of concrete structures
  23. Radio in Construction Monitoring
  24. Settlement Reducing Piles
  25. Land Surveying and Total Station Monitoring
  26. Vibration Monitoring
  27. Monitoring the complete strain history of concrete elements
  28. Past CMCS Projects

To reduce the settlement and bending stresses in the heavily reinforced raft supporting the QEII Conference Centre Westminster a limited number of piles were installed. The foundations were constructed by John Mowlem Ltd. The load cell used to monitor the load in the pile at the raft interface as well as raft presure cells were designed and installed by G Price and I F Wardle, while at the Building Research Establishment. The photograph opposite shows the top down construction of the basement at the founding level.

The photographs above show the various stages of construction of the load cell. The left photo shows the preparation of the pile for the load cell. The middle photo shows the completed load cell fitted with its 3 mm soft membrane and reinforcing bars with pressure pads to link with the raft. The right photo shows the first layers of the raft reinforcement installed around the cell.

The above plot shows the load carried by the pile. The reduction in load in 1981 was due to the foundation contractor removing his plant from the site. The rapid increase in load was due to the main building works, followed by the less steep fitting out stage. Since January 87 there has been a slow reduction in load, thought to be due to a rise in the water level in the area. The general fall in load was also recorded by 4 raft pressure cells. The load cell and the raft pressure cells only monitor effective pressure, i.e. water pressure can pass either side of the soft membrane.

 
 
Home Page Tunnels Embankments Bridges Retaining Walls Pile Monitoring Buildings Environmental Surveying
Home Page Information Sheets Software - LogSafe Hardware - Data Acquistion Instrumentation
Home Page Taplow Pipe Jack Cheval Place St Andrews Hall Canonbury Tunnel Euston Covent Garden
Information